Efforts are underway to try and recoup some of the costs that caused the construction of the now finished Sylvan Valley Industrial Facility on Ecusta Road to run over its initial budget.

During its recent meeting, the Transylvania County Board of Commissioners approved the final budget total for the project – $5,339,708, which is $621,408 above the original budgeted amount to build the 60,000-square-foot building, which currently houses SylvanSport and has an additional 30,375 square feet available for another business/industry.

The amount above the original budget includes $405,744 in...